SECORD

FOUR LAKES TASK FORCE DAM UPDATES

Crews are working steadily to prepare for gate installation. Last month, all pier walls were completed, allowing work to begin on the primary spillway baffle blocks and end sill. Significant progress was made on the rehabilitation of the controls building. They installed a new brick façade and began installation of the roof and staircase. The left embankment extension work was nearly completed bef…